You are currently browsing the archives for the Connection Charges category.
| M | T | W | T | F | S | S |
|---|---|---|---|---|---|---|
| « Dec | ||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| 8 | 9 | 10 | 11 | 12 | 13 | 14 |
| 15 | 16 | 17 | 18 | 19 | 20 | 21 |
| 22 | 23 | 24 | 25 | 26 | 27 | 28 |
| 29 | 30 | 31 | ||||
20/05/2009 by David Slade.
Grid Connected Generation
Terminology to Start
• Developer
– You!
• Distribution Network Owner/Operator (DNO)
– Owns, maintains, develops and operates the physical network
– SP Manweb, United Utilities in the North West
– Not the slightest bit interested in selling or buying energy from you
• Electricity Supplier
– Party to contract with to buy & sell energy
– Npower, PowerGen, Scottish Power, British Gas, etc…
– Not the slightest bit interested in the physical connection
• Ofgem
– Electricity and Gas Market regulator
– Also administers the ROC process if your technology is eligible
Just Some of the Legal Issues
• If grid connected, then it is a legal requirement to have permission to connect & operate any form of generation
– Needs to have a DNO connection agreement
– Needs to have correct electrical protection
– Needs to have correct earthing
– Needs to have an export meter (if exporting)
– Needs to have a supplier contract (if exporting)
• D-code : Distribution Code for UK Distribution Networks
• G-code : Grid Code for UK Transmission Networks
• Electricity at Work Regulations
Engineering Recommendations
• Technical connection requirements are detailed in the Engineering Recommendations
– DNOs view these as “Rules” rather than just “Recommendations”
• G83: Less than 6kW (16A/phase)
– No connection agreement required but must notify DNO once on
• G59: Less than 5MW and less than 20kV connection
– Must have a connection agreement
• G75: Anything else up to 50MW or transmission connected
– Must have a connection agreement
DNO Responsibilities
• Statutory obligations under the terms of their licence
– Secure operation and development of the network
– Safe & reliable operation of the network
– Ensure fair and equal access to the network
– Least cost options for connection
– Lifetime of network not just your connection
• Must respond to a connection application within 90 days. Remember, they’re not out to get you, but they have responsibilities too!
Electrical Connection Issues
• Technical issues to be considered during connection study/investigation
– Thermal limits
– Voltage limits & step change
– Reverse power-flows through transformers
– Short-circuit rating of switchgear
– Protection arrangements & co-ordination
– Harmonics & Power Quality
– Transient stability (usually only for larger generators)
• Energy Metering
• There will be the need to provide a reasonable level of data on the generator and the site connections
• The connection and protection will need to be witnessed and approved by the DNO in order to complete the connection process
Network Capacity Issues
• The Distribution Network has real limits
• Due to load growth and the drive towards maximising use of existing assets, available headroom is often quite limited
– Cable ratings reached during peak load
– Voltage drop/rise reached
– Circuit breaker short-circuit limits reached
• The Capacity Race
– It is not just fiction it is unfortunately real in some locations
– First-come, first-served & Interactive Applications
– There are some solutions but most do add cost and complexity
Rule of Thumb Connection Capacities
< 6kW 240V
< 1MW 415V (3-phase)
< 1-10MW 11kV
< 30MW 33kV
< 50MW 66kV/132kV
> 50MW 132kV upwards & National Grid interfaces…
As with any project, the bigger the project, it is important that you have the right level of advice or expertise to de-risk the project.
So, what do I do to get connected?
• Contact your friendly neighbourhood consultant ☺
But seriously:
• Start with a rough idea of what you want to do
– Check that your site can fit it and you can afford it
– Check that all other regulatory issues are okay
• Have an informal “chat” about connection possibilities with DNO generator connections or knowledgeable person
– Check that your initial idea still sounds sensible
When contacting the DNO
• Contact DNO – generation connections (NOT Demand)
– The connection process will be more likely to be successful with good communication between the developer and the local DNO
• Determine your connection route: G83, G59 or G75
– This may have costs associated with it
• Be prepared for a process not just rubber stamping
– Planning & Information phase
– Detailed Design phase
– Installation phase
– Testing & Commissioning phase
Working with the DNO
• Seek an early meeting to discuss your project
– Outline the scheme
– Discuss the DNO’s process for connections
– Request an indicative connection design and budgetary cost estimate with a split between contestable & non-contestable works
• Review your project
– Submit the formal connection application
– Remember to accept the connection offer!
• Submission of data to DNO
– Make sure that this is appropriate and timely to avoid delays
• Testing and Commissioning
– Plan in advance to avoid delays as staff will usually be quite busy
Connection Charges
• Application Fees
– These vary between DNO and size and voltage level of project
– Complex projects may involve additional fees
• Connection Assets
– Developer will be expected to pay full costs for all sole-use assets
• Generation Use of System Charges
– Site dependent & in lieu of network reinforcement costs
– Each DNO has own policy in-line with Ofgem guidance
Competition in Connections
• Developer as two options:
– Get the DNO to do all works necessary for the connection
– 3rd party to provide all contestable works which DNO then adopts
• Contestable Works
– Supply & installation of any new assets up to the point of connection to the existing network. Adoption agreement required.
• Non-Contestable Works
– Any studies, reinforcement or installation on existing network
– Design & specification of any new assets, consents & way-leaves
• Note: The DNO will not get involved in any “on-site” works
Finally, just when you thought it was too easy
Other non-electrical issues still need to be resolved
– Planning Permission?
– EIA, Emissions?
– Health & Safety?
– Commercial?
– Installation & transport?
– CDM?
Posted in G75, Connection Charges, Contestable Works, Non-Contestable Works, G59, G83, Energy, metering, Ofgem, NDO's | Print | No Comments »